Sequence of products used in bathroom renovation

Einklappen
X
 
  • Filter
  • Zeit
  • Anzeigen
Alles löschen
neue Beiträge

    Sequence of products used in bathroom renovation

    Hello,

    we want to create a cement bathroom and I have a few questions regarding the sequence and amounts of cement/products needed.

    Our room: We want to divide the bathroom into a wet and a "dry" area. The wet area will involve a shower and bath. The dry area will contain a toilet and sink. We want a concrete finish on all walls and on the floor of the "wet" area.
    The surfaces are either concrete (floor wet area ca 4 sqm), Plasterboard (1of two shower walls, 2qm m) and stone wall without plasterboard ( 2sq m - one wall in the shower and all other walls).


    Is this the right sequence of products:


    1.) Waterproofing Grout "DSB DIchtschlämme", 2-3 layers, 2mm thick in total- 1,6kg per mm thickness (per meter?)
    --> I will use DSB for the plasterboard-wall in the shower, right? Do I also use it for the part of the plasterboard-wall in our bathroom which is never in direct contact with water?

    2.) SQ Primer, applied to all surfaces

    3.) For Plasterboard Surface: KLEMO adhesive mortar including light mesh

    4.) Marfino Concrete 400 - 800g / sq m, two layers needed: Everywhere. DYE mixed into it according to our wishes?

    5.) PUR2 Polycoat as a finish everywhere


    In regards to all the walls/ceiling which are not in direct contact with water: Is it possible to use regular concrete for these and paint them? Or should every wall in a bathroom be plastered with Marfino / PUR2?

    Thanks a lot for the help!

    #2
    Hello, Sonja,

    The most elaborate case is a shower where the wall is made of plasterboard. Here the following order would be correct:

    1) Two coats of DSB sealing slurry to prevent moisture from penetrating the substrate.
    2) At the earliest one day later a layer of KLEMO with inserted armour fabric to ensure that there is a good connection to the substrate and that no cracks can develop in the surface.
    3) At the earliest two days later a layer of MARFINO, applied with a Venetian smoothing trowel. MARFINO can be dyed with cement-proof pigments as desired.
    4) At the earliest one day later, sanding of the surface, if desired.
    5) If the surface is not yet smooth enough or if the substrate shimmers through, a second coat of MARFINO can be applied in the same way.
    6) At the earliest one day later, two coats of LFC silicification to increase the surface hardness.
    7) At the earliest one day later, two coats of PUR-2 finish so that the surface does not absorb water and can be easily cleaned later.

    On walls where there is no splashing water or where the surface is not sensitive to splashing water, you can omit part (1). This also applies to a tiled surface.

    Parts (6) and (7) are also only important where there is splashing water. If this is not the case, you can also choose a different finish. My suggestion would then be a coating with LFC silicification and the next day a coating with H10 impregnation.

    Sven

    Kommentar


    • dr.backstein
      dr.backstein kommentierte
      Kommentar bearbeiten
      DEUTSCHE FASSUNG

      Hallo Sonja,

      Der aufwendigste Fall ist eine Dusche, in der die Wand aus Gipskarton besteht. Hier wäre folgende Reihenfolge richtig:

      1) Zwei Anstriche aus DSB Dichtschlämme um zu verhindern, dass Feuchtigkeit in den Untergrund eindringen kann.
      2) Frühestens einen Tag später eine Lage KLEMO mit eingelegtem Panzergewebe um sicherzustellen, dass eine gute Verbindung zum Untergrund vorliegt und keine Risse in der Oberfläche entstehen können.
      3) Frühestens zwei Tage später eine Lage MARFINO, die mit einer Venzianischen Glättkelle aufgetragen wird. MARFINO kann dabei nach Wunsch mit zementechten Pigmenten eingefärbt sein.
      4) Frühestens einen Tag später Schleifen der Oberfläche, falls das gewünscht ist.
      5) Falls die Oberfläche noch nicht glatt genug ist oder der Untergrund hindurchschimmert, kann eine zweite Schicht MARFINO in gleicher Weise aufgetragen werden.
      6) Frühestens einen Tag später zwei Anstriche mit LFC Verkieselung zur Steigerung der Oberflächenhärte
      7) Frühestens einen Tag später zwei Anstriche mit PUR-2 Endbehandlung, damit die Oberfläche kein Wasser aufnimmt und sich später leicht reinigen lässt.

      An den Wänden, wo es kein Spritzwasser gibt oder wo der Untergrund gegen Spritzwasser unempfindlich ist, kannst Du den Teil (1) weglassen. Das gilt auch für einen gefliesten Untergrund.

      Auch die Teile (6) und (7) sind nur dort wichtig, wo es Spritzwasser gibt. Wenn das nicht der Fall ist, kannst Du auch eine andere Endbehandlung wählen. Mein Vorschlag wäre dann ein Anstrich mit LFC Verkieselung und am nächsten Tag ein Anstrich mit H10 Imprägnierung.

      Sven

    #3
    Thanks a lot!